LA Metro – Limited D Line Service Due to Construction

March 19, 2023

    On Monday, March 20, and continuing for approximately 30 days, D Line (Purple) service will be interrupted due to the construction of the Purple Line Extension Project.

    During this time, the D Line will only run between Wilshire/Western and Wilshire/Vermont Stations.  

     

    Plan your trip with Moovit for updated schedules and routes.

     

    Transfers between the B (Red) and D (Purple) lines will be available at Wilshire/Vermont. This work begins the connection of the existing D Line stations with the new D Line Extension Project. 

    D Line will run as a shuttle between Wilshire/Western and Wilshire/Vermont every 20 minutes with 4-car trains. We’re single tracking on the D Line because of the work. 

    B Line service between Union Station and North Hollywood will run every 10 minutes with 6-car trains during midday and every 20 minutes in the early morning and late evenings. After approximately 30 days, trains will return to current service levels.  

    The Purple Line Extension Project will extend the subway from its current terminus at Wilshire/Western for nine miles to Westwood. The project is being constructed in three sections. The first section between Wilshire/Western and Wilshire/La Cienega is scheduled to open in 2024. 

     