Moovit Updates

Transbay Terminal Temporarily Closed

salesforce building moovit

All transit operators will temporarily provide bus service out of the nearby Temporary
Transbay Terminal at Howard and Main streets until all inspections are complete. The
closure is effective immediately.

Crews today discovered a fissure in one of the steel beams in the
ceiling of the third level Bus Deck on the eastern side of the Salesforce Transit Center
near Fremont Street. Out of an abundance of caution, the Transbay Joint Powers
Authority, after conferring with design engineers and contractors, will temporarily
close the transit center as the agency works with Webcor/Obayashi and structural
engineers Thornton Tomasetti to investigate and repair this issue and conduct an
exhaustive inspection of all steel beams throughout the transit center. Inspections have
begun.

You ride, we guide. 

Exit mobile version